Process
Every Metallic Epoxy Countertop installation requires a minimum of TWO(2)* Working Days to complete.
*Subjected to work area and environment conditions
Day 1
Morning
- Commencement of protection works
- Removal of kitchen appliances such as cooking stove and water taps (if necessary)
- Metallic Epoxy Self-Levelling Compound layer application (if necessary)
- Metallic Epoxy Base Primer layer application
Afternoon
- Pre-epoxy checks and touch-up works (if necessary)
- Commencement of Metallic Epoxy Design layer
The work area will then be sealed off to prevent dust and unwanted foreign objects from coming into contact with our Metallic Epoxy as it cures and hardens.
Day 2
Morning
- Post-epoxy checks and touch-up works (if necessary)
- Selected Metallic Epoxy Topcoat layer application
Afternoon
- Final epoxy and topcoat layer checks and touch-up works (if necessary)
- Removal of protection works and clean up
- Re-installation and testing of kitchen appliances
- Silicone application and final clean up
- Project Conclusion and handover